Friday, August 28, 2009

We have waffles!

The waffle pods were fully installed today. It now looks like they just need to pour the concrete for the slab! Looks like it would have been a fair bit of work they did today!

Thursday, August 27, 2009

Latest picture


Hopefully I can get there before dark next time. Getting a bit hard to see. Will be better when the days are longer.

Steel


Rio ready to go for the slab, hopefully in the next couple of days. Bring on the waffles and concrete!

Pipes and electrical

Pipes put in today.

Piers in

Piers were put in
on Wednesday

Monday, August 24, 2009

slab framework

The framework for the slab was done today. It all looks to be in the right place.

Sunday, August 23, 2009

We are getting close!


Finally we have something happening on the land!

bathroom Instalation

Our Bathroom has been installed on our land.

Friday, August 21, 2009

Slab

Slab should be laid late next week!

Sunday, August 9, 2009

latest update

Here is what the house looks like this weekend. Yep, same as last weekend. Plenty of space to pitch a tent!

Wednesday, August 5, 2009

Excavation

The land has been cleared and leveled now. The bank has also given the go ahead so we should be right to go full steam ahead very soon!